Building plan revision and engineering letter from Belt Engineering to address ISR concerns and prior inspection comments: "A revision is needed as the span beam that was done on a separate permit was not factored into the pool plans. Per Inspections Supervisor Joel Perdomo - "The contractor will need to amend their plans via an approved revision. The 5 foot green space along the waterway is a stormwater requirement, so if the other permit contains conflicting information, that prevents this scope from being executed, then this revision will need to account for that conflict and demonstrate an acceptable alternative." Please revise pool plans to include the span beam between the seawall and the pool deck. Once revised plans are approved reschedule inspection."
Bayshore Estates No 4, Lot 7