Vested under FBC 7th Edition. Construction of the new checkpoint at Airside E requires that the existing loading dock area be relocated for the duration of the construction phase, thus requiring an alternate route for deliveries that impacts one of the existing egress paths at the bottom of stair F6 per original design documents. As a result, we will be redirecting this operation from the south side of the APM shuttle to the north side. This presents some revisions to the stair core and to the loading dock operations to maintain continuity of exit paths, and to prevent the mixing of egress with other airport operations, including the moving of goods and services into the building. This Building Plan Revision includes: 1. A Memo from AECOM detailing the Temporary Egress Analysis 2. Signed/Sealed Plan Sheet - A0.103E - ASE - Ramp Level Temp Egress - Area 3 3. Signed/Sealed Letter from the Fire Protection Engineer certifying compliance of the applicable fire protection & life safety provisions