Building - 5 Applied - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-04-26
Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2023-04-26
Demolition Placard Required
A demolition placard is required on this record. Previous permit BDE-17-0438473 expired with no inspections. A demo pre-construction inspections and Demo-Final must be approved on this record before this permit can be issued
Informational • 2023-05-19
Termite Cert
Termite Certification Required
Informational • 2023-05-19
Utilities - Certificate of Occupancy Hold for Wastewater
—