Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-05-19
Water Commitment Required
Per conversation with Courtney Cadiz, this permit is for the improvement of an unimproved space to white-box status, which will then come in for permitting again once a tennant decides to build out
Informational • 2023-06-27
Building - 2 Applied, 1 Complied, 2 Released - Building Permit - Revision Record Associated to this Project
There is a revision record associated to this record
Informational • 2023-08-23
Final Private Provider Inspection Report Required
Final Private Provider Inspection Report Required
Informational • 2024-06-13
Utilities - Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2024-06-26