Utilities - Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2023-06-20
Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2023-06-20
Building - 1 Not Applicable, 2 Applied - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2024-04-15