Reissued and the original date: 09/13/2023: Project provides for improvements to the existing Filter Building, associated site improvements, and existing facility demolition at the City’s Morris Bridge site. Work includes retrofitting the roof of the Filter Building, removing sediment and vegetation at the three stormwater ponds, and demolishing tanks, building, concrete pavement, and piping.
$4,363,025.00
That Part Of Sections 23 And 24 Desc As Beg, 2632.49 Ft S Of Ne Cor Of Sec 23 And Run E 679.56, Ft S 420.88 Ft S 10 Deg 37 Min 07 Sec E 1166.17 Ft, W 1616.49 Ft N 17 Deg 04 Min 19 Sec W 354.31 Ft