Stop Work Order
All construction work is required to cease until terms and conditions of Order are satisifed
Informational • 2023-03-29
Building - 7 Applied - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-09-08
Utilities - Utility Application Submittal
A Utility application must be submitted before the Building Permit can be issued
Informational • 2023-09-08
Wastewater Commitment Required
A Wastewater Commitment may be required for this building project. Upon review of the Utility application, If the Wastewater department determines that a Wastewater Commitment is required, the Building permit will not be issued until the Wastewater Commitment is issued and all related Utility fees are paid
Informational • 2023-09-08
Water Commitment Required
A Water Commitment may be required for this building project. Upon review of the Utility application, If the Water department determines that a Water Commitment is required, the Building permit will not be issued until the Water Commitment is issued and all related Utility fees are paid