NSF Fee Due
E-Check NSF Fees due- (No account/unable to locate account) Original amount due on (BLD-23-0502287) $269.39+ NSF Fee due $30.00= Total amount due $299.39
Informational • 2023-08-02
Building - 1 Applied, 1 Complied, 4 Released - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-09-19
Certificate of Occupancy Hold for Water
Due to minimal plumbing changes, the existing 3-inch domestic meter (serial no. 31950578) is adequate. Water Commitment not needed. Backflow devices are compliant
Informational • 2023-11-01
Utilities - Wastewater Commitment Required
A Wastewater Commitment may be required for this building project. Upon review of the Utility application, If the Wastewater department determines that a Wastewater Commitment is required, the Building permit will not be issued until the Wastewater Commitment is issued and all related Utility fees are paid
Informational • 2023-11-07
Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2023-11-07