Building - 5 Applied, 1 Complied, 3 Released - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-10-10
Utilities - Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2023-10-10
Final Private Provider Report Required
Final Private Provider Report Required
Informational • 2023-10-11
Building Plans - Deferred Submittals
The building official approves of the listed deferred submittal items presented in CBO-24-0000008 for shoring and reshoring, aggregate piers, post-tension tendon layout and friction loss calculations, structural steel connections, storefront systems, cold-formed steel framing, and metal fabrications, including stairs, ladders, and railings. The deferred submittal items shall not be installed until the deferred submittal documents have been approved by the revision record to the BLD record. The condition will be affirmatively noted on the record as a revision to the record and the revision will be required prior to the installation of said deferrals on site
Informational • 2024-02-20
NSF Fee Due
NSF Fee due - Original amount due on (bld-24-0504183-9) $522.75+ NSF Fee due $40 = Total amount due $562.75 Only charging the fee on one record as one time courtesy