Default - 1 Complied - NOC Required - Notice of Commencement Required
Notice of Commencement is required to be uploaded to the permit record prior to the requesting 1st inspection
Informational • 2023-11-08
Building - 1 Applied, 1 Complied - Building Permit - Stop Work Order
All construction work is required to cease until terms and conditions of order are satisfied. SWO FEE due. The Professional Engineer (PE) must ensure that all inspection reports are uploaded to the record, along with a digitally signed final report confirming that all work has been completed. Schedule a general progress check inspection through Accela
Informational • 2025-05-29
Final Threshold Report Required
Final engineer report is okay
Informational • 2025-06-16