Building - 1 Applied, 1 Complied, 1 Not Applicable, 4 Released - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-12-06
Utilities - Utility Application Submittal
A Utility application is not required
Informational • 2023-12-11
Wastewater Commitment Required
A Wastewater Commitment is not required for minimal plumbing
Informational • 2023-12-11
Water Commitment Required
A Water Commitment may be required for this building project. Upon review of the Utility application, If the Water department determines that a Water Commitment is required, the Building permit will not be issued until the Water Commitment is issued and all related Utility fees are paid
Informational • 2023-12-11
Final Private Provider Report Required
Final Private Provider Report Required
Informational • 2024-03-19