Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-12-27
Utilities - Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2023-12-27
Default - 1 Complied - NOC Required - Notice of Commencement Required
Notice of Commencement is required to be uploaded to the permit record prior to the requesting 1st inspection
Informational • 2023-12-27
Building - 3 Applied - Building Permit - Revision Record Associated to this Project
There is a revision record associated to this record
Informational • 2024-09-18