Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-12-29
Building - 6 Applied, 1 Released, 1 Complied - Building Permit - Demolition Record Required
Demolition record BDE-24-0443407 is required to be issues at the time of building issuance of BLD-24-0506057
Informational • 2024-01-29
Approved Blower Door Test Form Required
Residential buildings and dwelling units that have a permit application date of July 1, 2017 or later will require a Blower Test performed by an approved third-party. Blower Door Testing reports verifying seven (7) air changes per hour or less must be uploaded to the Accela project record. The Certificate of Occupancy will not be issued until the approved test is accepted by the City. Buildings with less than 3 air changes per hour will require a whole house ventilation system in accordance with M1507.3. Please visit our website to access the form (https://www.tampagov.net/sites/default/files/public%3A/additionalfiles/blower_door_test_form_final.pdf)
Informational • 2024-02-27
Termite Cert
Termite Certification Required
Informational • 2024-02-27
Pending BLD-24-0506063 Rev. 1 plans with property lines and easements
Record locked until BLD-24-0506063 Rev. 1 plans with property lines and easements is approved
Informational • 2024-12-10