Building - 1 Applied, 2 Complied, 1 Released - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2024-05-06
Default - 1 Complied - NOC Required - Notice of Commencement Required
Notice of Commencement is required to be uploaded to the permit record prior to the requesting 1st inspection
Informational • 2024-05-06
Termite Cert
Termite Certification Required
Informational • 2024-08-21
Utilities - Certificate of Occupancy Hold for Water
Per SwiftComply, the backflow device is complaint
Informational • 2024-08-21
Final Private Provider Report Required
Final Private Provider Report Required
Informational • 2024-08-22