Building Plans - SECURE PLANS
Office Development - Site Size
Informational • 2017-05-24
Utilities - Utility Application Submittal
A Utility application must be submitted before the Building Permit can be issued. Please contact Water directly at (813) 274-7405 or WaterCommitment@tampagov.net
Informational • 2024-10-01
Wastewater Commitment Required
Project has minimal plumbing only with no change of use. Water department has determined that the existing meter is adequate and there is no increase in ERCs; therefore, no wastewater review is required. If you have any questions, comments, or concerns, please contact Tyler Albright at Tyler.Albright@tampagov.net
Informational • 2024-10-01
Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied. Please contact Wastewater directly at (813) 274-8065 or WastewaterCommitment@tampagov.net
Informational • 2024-10-01
Building - 6 Released, 1 Applied - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2025-01-27