Building - 1 Applied, 1 Not Applicable - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2024-10-23
Default - 1 Complied - NOC Required - Notice of Commencement Required
Notice of Commencement is required to be uploaded to the permit record prior to the requesting 1st inspection
Informational • 2024-10-23
Electrical Contractor Required
A change of contractor form is required to be submitted to replace electrical contractor. William Macklin (EC13007403) stated that his license is being used on this permit without his permission. His statement has been uploaded to the record. A new electical contractor is required on this record since electrical inspection was already conducted