Building Plans - Deferred Submittals
The building official approves of the listed deferred submittal items presented in CBO-23-0000125 Rooftop Accessories, Decorative Aluminum Railings, Pre-Engineered Wood Components, Pre-Engineered Wood Trusses, Aluminum Louvers and Electrical Switchboard Coordination Study. The deferred submittal items shall not be installed until the deferred submittal documents have been approved by revision record by the building official or designee. The condition will be affirmatively noted on the record as a revision to the record and the revision will be required prior to the installation of said deferrals on site
Informational • 2022-12-02
Building - 1 Complied, 1 Applied - Building Permit - NSF Fee Due
NSF - Refer to maker NSF Fee due - (Refer to maker) Original amount due on (BLD-25-0513516) $45,650.36 + NSF Fee due $2,282.52 = Total amount due $47,932.88
Informational • 2025-05-12