Termite Cert
Termite Certification Required
Informational • 2024-08-02
Building - 2 Applied - Building Permit - Field Review of TRZ Lot
Met in the field with Shane O'Neil with Vikin Homes- Lot corners were staked, setbacks were staked and TRZ zone was staked. Result is that the 38" and 44" trees are in the TRZ and are allowed to be removed. Shane to revise site plan in accordance with field verification. See uploaded field notes. Also reviewed for canopy conflict approximately 2 cuts 4" or less
Informational • 2024-08-22