Building - 1 Applied, 1 Not Applicable - Building Permit - EPC wetlad Delineation and Approval required
EPC wetland delineation required and EPC approval of new seawall and storm water improvements required prior to permitting
Informational • 2022-02-09
Mitigation required and code enforcement action will require additional fees
See Code Case results in workflow. Triple permit fee for non hazardous grand trees ($619.x 3)has been paid for removal for removal of two (2) grand trees and (5) protected trees without a permit. In addition to the triple permit fee, 226" of replacement @ $150. per inch due for replacement at $33,900.00. Potential of additional code enforcement action requiring a fee of $15,000.00 per tree based on the damage being irreversible or irreparable imposed by special magistrate
Informational • 2022-02-09