As-Built Topo Survey
An As-Built Topo Survey will need to be uploaded to the record before the BLD - Final inspection is scheduled, in order to confirm that all illegal fill was removed from the site and the required elevations have been re-established
Informational • 2023-07-18
Building - 3 Applied, 1 Complied - Building Permit - C/O hold for site plan revision
site plan revision required to reflect approved tree removal oak rear left
Informational • 2023-09-18
tree mitigation
24 type 1 trees owed mitigation
Informational • 2023-09-18
Stop Work Order
All construction work is required to cease until terms and conditions of Order are satisifed
Informational • 2025-03-21