Demolition Placard Required
A demolition placard is required on this record
Informational • 2023-12-21
Building - 6 Applied, 2 Released - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-12-26
Utilities - Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2023-12-26
Flood Elevation Certificate Required
Flood Elevation Certificate Required
Informational • 2024-02-05
Building Plans - Deferred Submittals
The building official approves of the listed deferred submittal items presented in CBO-25-0000037 for a pre-engineered metal structure, aluminum canopy, roll-up door, crane system, and cage ladder. The deferred submittal items shall not be installed until the deferred submittal documents have been approved by a revision to the BLD record (BLD-24-0505945). The condition will be affirmatively noted on the record and the revision will be required prior to the installation of said deferrals on site
Informational • 2025-04-30