Utilities - Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2024-04-03
Final Private Provider Inspection Report Required
Final Private Provider Inspection Report Required
Informational • 2024-04-08
Required mitigation, penalty trees and payment to the tree trust.
Mitigation and penalty trees are required for all trees that were removed without permit and referenced by Tree numbers 1-36 and 48-66. The required mitigation is 72 type 1 trees, 20 type 3 trees and 12 palms. 43 three inch penalty trees are required. All mitigation and penalty trees have been invoiced to the tree trust. A complaint has also been issued, payment to the tree trust is required to close the complaint. and to call for inspection. If you have any questions, please call Natural Resources. The total required payment is $50550
Informational • 2024-10-17
Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2024-10-25
Building - 5 Applied, 1 Released - Building Permit - Revision Record Associated to this Project
There is a revision record associated to this record
Informational • 2025-07-02