Transportation Mitigation Due
PRIOR TO THE ISSUANCE OF A BUILDING PERMIT ASSOCIATED WITH THE CHANGE OF USE FROM OFFICE TO RETAIL OR RESTAURANT THE DEVELOPER WILL PAY THE CITY OF TAMPA A TRANSPORTATION MITIGATION FEE OF $13,894 TO BE PAID AT A RATE OF: $979.97 PER 1,000 SQUARE FEET. THE TOTAL TRANSPORTATION MITIGATION FEE PAID SHALL NOT EXCEED $13,894
Informational • 2023-09-19
Building - 1 Applied, 3 Complied, 1 Released - Building Permit - Site Meeting Required
Site meeting required with Supervisors and area inspectors, due to excessive failed inspections. A meeting has been scheduled with GC and trades for 1:00pm on 06/11. This lock will be released by Supervisor Morgan or Lewis upon completion of the meeting
Informational • 2024-06-05
Transportation Mitigation Fee per REZ-22-72 $13,894 Before permitting
Transportation Mitigation Fee per REZ-22-72 $13,894 Before permitting
Informational • 2024-10-03
Flood Elevation Certificate Required
Flood Elevation Certificate Required
Informational • 2024-10-04
NSF Fee Due-
NSF Fee Due (Corporate not authorized) on BLD-23-0501795. Original amount due $88.12 = NSF Fee due $30.00= Total amount due $118.12
Informational • 2025-02-06