Transportation Mitigation Due
PRIOR TO THE ISSUANCE OF A BUILDING PERMIT ASSOCIATED WITH THE CHANGE OF USE FROM OFFICE TO RETAIL OR RESTAURANT THE DEVELOPER WILL PAY THE CITY OF TAMPA A TRANSPORTATION MITIGATION FEE OF $13,894 TO BE PAID AT A RATE OF: $979.97 PER 1,000 SQUARE FEET. THE TOTAL TRANSPORTATION MITIGATION FEE PAID SHALL NOT EXCEED $13,894
Informational • 2023-09-19
Default - 1 Complied - NOC Required - Notice of Commencement Required
Notice of Commencement is required to be uploaded to the permit record prior to the requesting 1st inspection
Informational • 2024-04-12
Building - 1 Applied, 1 Released - Building Permit - Revision Record Associated to this Project
There is a revision record associated to this record
Informational • 2024-09-11