Flood Elevation Certificate Required
Flood Elevation Certificate Required
Informational • 2022-08-24
Building - 3 Applied - Building Permit - Transportation Mitigation Fee per REZ-22-72 $13,894 Before permitting
Transportation Mitigation Fee per REZ-22-72 $13,894 Before permitting
Informational • 2022-11-23
Transportation Mitigation Fee per REZ-22-72 $13,894 Before permitting
Transportation Mitigation Fee per REZ-22-72 $13,894 Before permitting
Informational • 2022-11-23
Planning - 1 Complied - Transportation - PERMIT HOLD: transportation mitigation due
PRIOR TO THE ISSUANCE OF A BUILDING PERMIT ASSOCIATED WITH THE CHANGE OF USE FROM OFFICE TO RETAIL OR RESTAURANT THE DEVELOPER WILL PAY THE CITY OF TAMPA A TRANSPORTATION MITIGATION FEE OF $13,894 TO BE PAID AT A RATE OF: $979.97 PER 1,000 SQUARE FEET. THE TOTAL TRANSPORTATION MITIGATION FEE PAID SHALL NOT EXCEED $13,894. THESE PAYMENTS WILL BE USED FOR TRANSPORTATION IMPROVEMENTS IN THE VICINITY OF THE SITE
Informational • 2024-03-07