Building - 3 Applied, 2 Complied, 3 Released - Building Permit - Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-05-10
Utilities - Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2023-05-10
FEMA elevation certificate
FEMA flood elevation certificate required prior to C/O
Informational • 2023-06-02
NSF Fee Due
NSF - Refer to maker NSF Fee due - (Refer to maker) Original amount due on (BLD-25-0513516) $45,650.36 + NSF Fee due $2,282.52 = Total amount due $47,932.88
Informational • 2025-05-12
Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2025-07-08