Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2023-10-25
Certificate of Occupancy Hold for Wastewater
If it is determined by the Wastewater department that a Wastewater Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Wastewater utility requirements have been satisfied
Informational • 2024-04-26
Building - 2 Applied, 4 Complied, 2 Released - Building Permit - Revision Record Associated to this Project
There is a revision record associated to this record
Informational • 2024-04-29
Utilities - Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2024-11-14
Termite Cert
Termite Certification Required
Informational • 2024-11-22