Please see Impact Fee Calculation Sheet
Please see Impact Fee Calculation Sheet
Informational • 2024-04-23
Utilities - Certificate of Occupancy Hold for Water
If it is determined by the Water department that a Water Commitment is required for this building project, the Certificate of Occupancy will not be issued until all Water utility requirements have been satisfied
Informational • 2024-04-23
Utility Application Submittal
A Utility application must be submitted before the Building Permit can be issued. Associated utility UTL-22-0001445
Informational • 2024-05-22
Termite Cert
Termite Certification Required
Informational • 2024-07-03
Building - 4 Applied, 4 Released - Building Permit - Revision Record Associated to this Project
There is a revision record associated to this record
Informational • 2025-02-06